Winter construction measures for metal workshop building

Time:[2021-11-24]  Hits:2731

a. The winter construction of steel structure production and installation shall be carried out strictly in accordance with the relevant steel structure winter construction regulations.

b. When steel components are installed at positive temperature and at negative temperature, the shrinkage of components should be considered according to the difference in ambient temperature, and technical measures to adjust deviation should be taken during construction.

c. Welders who participate in the construction of negative temperature steel structures should undergo negative temperature welding process training, pass the examination, and obtain corresponding certificates.

d. The steel and related connecting materials used under negative temperature must be accompanied by a quality certificate, and the performance meets the requirements of the design and product standards.

e. The welding rod used under negative temperature shall not be exposed for more than 2 hours, and it shall be re-baked after more than 2 hours, and the number of baking of the welding rod shall not exceed 3 times.


f. Bake the flux according to the regulations before use, so that the water content does not exceed 0.1%.

g. High-strength bolts used under negative temperature must have a product certificate, and the torque coefficient and axial force must be re-inspected under negative temperature.

h. The paint used for steel structure under negative temperature shall not use water-based paint.

i. When the component is blanked, a shrinkage margin should be reserved, and the welding shrinkage and compression deformation should be coordinated with the shrinkage deformation of the steel under negative temperature.

j. When assembling the components, expand the assembly from the inside to the outside according to the order stipulated by the process, and do a test during the assembly of the negative temperature to determine the shrinkage value of the weld that needs to be reserved.

k. When assembling components, remove rust, burrs, soil, oil, ice and snow and other debris remaining in the joint 50mm, and keep the joints dry and free of residual moisture.

l. Multi-layer welding should be used when welding steel plates above 9mm under negative temperature. The welds should be welded layer by layer from bottom to top. Each weld is completed at a time. If the welding is interrupted, the welding defects should be removed before welding again. It is strictly forbidden to start the arc on the welding base metal.

m. When the steel structure is installed on site, in case of snow or wind speed above 6m/s, set up a protective shed.

n. The unqualified welds shall be removed and re-welded, and the welding shall be carried out in accordance with the provisions of the welding process of the steel structure under negative temperature.

o. When the ambient temperature is lower than 0°C, perform the painting process test before applying the anti-corrosion coating. When painting, the rust, oil stains, burrs, etc. on the surface of the component must be cleaned up, and the surface must be kept dry. No painting work is allowed in snowy weather or when there is thin ice on the components.

p. Take anti-skid measures when transporting and stacking steel structures in winter. The component stacking site is flat and solid without puddles, and the ground is free of icing. When the components of the same model are stacked, the components should be kept horizontal, and the shims should be placed on the same vertical line to prevent the components from slipping.

q. Before the steel structure is installed, its quality shall be re-inspected according to the requirements under negative temperature conditions, and the components that have been missed in the production and deformed during transportation and stacking shall be repaired and corrected on the ground.

r. When using steel cables to hoist steel components, anti-skid spacers should be added, the gusset plate that is hoisted at the same time as the components, and the fixtures required by the installer should be tied firmly with ropes.

s. According to the temperature conditions, the steel component installation sequence chart is compiled, and the installation shall be carried out in strict accordance with the specified sequence during construction.

t. Prepare the welding process for steel structure installation, and both ends of a component shall not be welded at the same time.

u. Before installation, remove ice, snow and dew on the surface of the components, but do not damage the coating.

v. Columns and main beams installed at negative temperature shall be corrected immediately, and the correct position shall be immediately fixed permanently. The components installed on the same day shall form a stable space system.

w. When installing high-strength bolt joints, there must be no snow or ice on the friction surface of the components, and no contact with dirt, oil and other stolen objects.

x.In addition to complying with the requirements of "Code for Construction and Acceptance of Steel Structure Engineering" (GB50250-95), the quality of steel structure installation under negative temperature should also be inspected and accepted according to design requirements.

Copyright:佛山市勝邦鋼結構有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號
主站蜘蛛池模板: 水热反应釜厂家_水热反应釜价格_水热合成反应釜批发-仪贝尔仪器 - 水热釜,水热反应釜,水热反应釜厂家,水热反应釜价格,水热反应釜型号,水热反应釜内衬,水热反应釜25ml,水热反应釜50ml,水热反应釜100ml,水热合成反应釜 | 天天生活网_实用的生活常识网站、有趣的生活点滴小妙招分享 | 南京样本设计,彩页制作,宣传册设计,画册设计印刷,包装设计公司,南京台历制作 | 智能化会议系统|多媒体会议系统|无纸化会议系统|会议音箱|高清视频会议终端|智能化会议室|会议系统|视频会议系统-深圳市航视达科技有限公司 | 深山工作室提供网络投票系统|微信公众号投票|微信公众号小程序|抖音小程序|百度小程序|微信公众号开发|企业网站建设 | 真空清洗炉_真空煅烧炉_铸铝加热器-盐城市钰凯电器有限公司 | 天力普电力科技有限公司 | 意大利留学-意大利语培训-马来西亚留学【长青藤海外】 | 锦州龙威机械有限公司官网 ,锦州医药包装机,包装机,锦州包装机械,小袋颗粒装盒生产线,颗粒装盒生产线,软双铝装盒线,伺服颗粒 | 激光焊接机_激光打标机_激光切割机-惠州市镭凌激光科技有限公司 激光焊接不锈钢翅片管,不锈钢翅片管,激光焊接复合翅片管,南通拓帆换热设备有限公司 | 以物联网技术为核心专注于智能安防领域物联网服务的高新技术企业-北京欣智恒科技股份有限公司(官网) | 无土栽培|无土栽培技术|水肥一体化|无土栽培蔬菜 | 无人叉车|智能无人叉车|智能AGV叉车|激光叉车AGV厂家_江西丹巴赫机器人股份有限公司 | 天津佳创博为科技有限公司|AGV控制器|无人搬运车|磁导航传感器|AGV专业零配件 | 啤酒厂家_啤酒代工厂_原浆啤酒厂家 - 山东十谷啤酒有限公司 | 石家庄团建公司|石家庄拓展训练|石家庄拓展培训|石家庄公司团建|石家庄拓展公司-石家庄启聚团建公司 | 亦庄律师法律咨询|北京亦庄律师在线|-亦庄律师事务所 | 龙淼环保-旋流-喷淋塔,高温布袋,脉冲布袋-单机-滤筒除尘器,活性炭吸附箱,催化燃烧设备,除尘器配件-沧州龙淼环保设备制造有限公司 | 液位变送器_智能压力变送器_3051差压变送器_单双法兰,投入式,电容式,温度变送器-淮安润中仪表科技有限公司 | 太原铁艺围栏-山西泓宸辉铁艺工程有限公司 | 陕西筱润智能科技有限公司 干部人事智能档案柜 智能密集架 智能档案柜 部队选层文件智能柜 智能枪弹柜 财务智能档案柜 边防武警智能密集架 医院智能档案柜 部队选层文件智能柜智能枪弹柜 学校医院文件柜 企事业单位公检法智能文件柜 生产厂家-筱润智能科技有限公司 RFID射频智能密集架 全自动智能选层档案柜 智能密保柜 枪柜部队营房营具床桌椅办公家具 办公用品档案盒设备货架 全自动智能选层柜生产厂家-筱润智能科技有限公司 | 加药装置-排油烟装置-工业滤水器-连云港灵动 | 湖南净声源环保科技有限公司是一家专业从事噪声治理和建筑声学设计生态环境综合治理服务的企业,专业从事株洲电梯隔音治理,湘潭中央空调降噪处理,衡阳邵阳冷却塔噪音治理,岳阳常德大型风机噪声隔音降噪,张家界空压机噪声治理,益阳配电房变压器噪声治理,专业郴州永州工厂企业车间噪声治理,怀化娄底专业机械设备减振降治理,武汉噪音治理隔音降噪公司,孝感噪音治理,立式球磨机的噪声控制,专业隔音降噪公司,、以及各类机械动力设备减振降噪噪声治理的公司,同时为客户提供咨询与解决方案 | 泰州光明会计师事务所有限公司-财务业务审计,会计服务业务及资产评估业务的专业服务机构 | 喷涂流水线,喷漆流水线-山东天意设备科技| 渣浆泵厂家/潜水-渣浆泵过流件-管道增压泵 - 河北聚洪泵业有限公司 | 苏州交通设施_道路划线_停车场划线_厂区划线_环氧地坪厂家-推荐【飞扬市政交通设施公司】专注交通设施8年! | 贴标机_全自动贴标机_贴标机生产厂家_【佼佼者自动化】 | 上海家博会_2025上海家博会时间表_5月31-6月2日_上海家博会门票_免费领取入口 | 西安泰富西玛电机有限公司总部-电机-高压电机-西玛电机-西安西玛电机-泰富西玛电机-西安电机厂-西玛电机销售 | 推荐|广佛一条龙高端茶到底有多香 | 云南自考网_云南自学考试网| 潍坊卓瑞机械有限公司,输送设备,石灰消化设备,餐厨垃圾设备,化机浆设备,污泥脱水 | 企业旺旺-qy55.com| 绿夏技术导航 - 收录精选资源及优质站点网址! | 履带式移动破碎站-移动筛分站-移动碎石机-破碎机_山东奥凯诺矿机 | 长沙网站建设,网站设计制作,长沙小程序开发,公众号开发,长沙叶老设计 | 宁波搬家_宁波搬家公司_宁波搬厂_专业搬家搬厂-「宁波喜洋洋搬家公司」 | 衡水物流网,衡水物流信息网,衡水物流公司,衡水货运专线,衡水专线运输车辆 | 楼宇门厂家-氟碳漆门-不锈钢大门-单元门-锌合金大门-永康市龙卫门业 | 丝杆升降机-蜗轮-滚珠-螺旋-swl丝杠升降机-德州润驰减速机有限公司 |